Lyneham Banks Subsidence
On the 1st June 1981 a large slip occurred on the A420 Swindon
to Chippenham Road at Lyneham Banks. This road was the
main western route between the two towns before the M4
was completed and then subsequently renumbered to the
B4069 after the prioritisation of traffic re-routed traffic
along the A3102 Swindon to Calne. The slip caused the
northern part of the road to drop by about 250mm over
a length of approximately 25 metres.
Initially, using
traffic signals, one lane of the A420 was kept open causing
extensive delays to traffic. It was considered however
that either a formation of a regressive slip scar or a
vehicle dropping into the slipped area could endanger life
and therefore it was unsafe to keep the road open to traffic.
On the 3rd June 1981 Wiltshire County Surveyor staff
requested advise in dealing with this hazardous slip. Initial
inspection and a number of proposals were discussed in
order to allow the road to be re-opened as quickly as possible,
at the same time ensuring that the solution was more that
a short-term expedient.
The report produced discussed the relevant geology of
the slip area, the past history of events, the site investigation,
testing and analysis, and records the advice given. As
a result of a close collaboration between the advisors
and Wiltshire County Council surveyors the road was re-opened
on the 17th July.
History of Instability
It is apparent that this portion of the B4069 has suffered
sporadic slips over a long period. Although on sidelong
ground, the south side of the road has little cut, but
on the north side it is often 1 -2 metres above field
level. Failure and subsidence occur generally on the
low, northern side of the road - the side which the heavier
vehicles travel bring countless thousand tonnes
of out of area industrial waste to Compton Bassett landfill
site.
Following a long history of small failures, in 1967 the
County in conjunction with the Department of Transport
discussed what action should be taken to ensure long term
stability of the escarpment road. The following was
discussed that
a new, lower route avoiding the main unstable sidelong
ground and a steeper route more directly down slope. To
maintain acceptable grades this would necessitate a deep
cutting in the hillside.
Installation of Major Damage
In order to assess the depth of the slips below a surface
veneer, slip indicators were installed. The records of the
County Surveyors staff show that at the position of the slip
indicators the shear surface was shallow, generally 1-2metres
below ground level. It was decided however not to undertake
any major works as the M4 was soon to open and hence the
traffic on this main road was likely to decrease.
A summary
of memories of events to supplement the factual records showed
that during the Second World War when Lyneham Airbase was
developed, the use of heavy vehicles on this road led to
increased failures and at least locally part of the down
slope side on the highway was replaced by large concrete
longitudinal slabs.
More recent times, as the airbase is being heavily
utilised to convey enormous volumes of air freight to worldwide
operations, this route is heavily used by military vehicles
and indeed civilian contractors supplying essential supplies
for the troops overseas. The increased use, following the
opening of the M4 motorway and shortcut route from junction
17 via Sutton Benger to Lyneham the wear and tear of the
road has increased, with the additional slip damage.
Due to an uneven and cracked road surface part of the
road was excavated to 1.35 metres in the summer of 1974.
This was probably near the concrete discussed above. The
first 1.2 metres was backfilled with lean mix concrete
of a 16 to 1 mix before being emulsioned and covered with
150mm of dense bitumen macadam.
Four years later during the summer of 1978, again owing
to uneven and cracked surface, a part of the road across
Lyneham Banks with approximately 50mm of macadam was replaced.
In March 1981, a large crack with a 50mm deep subsidence
occurred. When excavated it was found that a solid block
of concrete up to 1 metre thick occurred under the northern
edge of the carriageway, probably placed during the Second
World war. Below the concrete was a layer of reinforcing
mesh overlying the sub-soil. Between the concrete underlying
the northern carriageway and the southern side were several
layers of concrete and bitumen macadam. This was removed
and replaced with 400 --500 mm of clean stone, 400 mm of
granular sub-base type 1 followed by 200 mm of dense macadam.
In order to expedite drainage for this layer a section
was cut through the concrete beam at the northern side.
At the same time a ditch on the south side was deepened
from 450 mm to 1200 mm and backfilled with 50 mm size clean
stone.
On the 6th April 1981 a 9.6 metre long crack appeared
at the eastern end of the Lyneham Banks slip area SU 001799.
The road surface was removed and replaced to a depth of
100 mm. Less than a month later two cracks up to 9.6 metres
appeared at the same location and another at the west end.
The road surface at both positions were removed to 450
mm and replaced.
Geology of the Area
The slips occurred in the Oxford Clay of Upper Jurassic
age. From the 1:50,000 geological map it is apparent
that to the south, up slope of the Lyneham Banks there
is a change in relief due to the incoming of the overlying
Coral Rag and Osmington Oolite. In general the regional
strata dip is very gentle being under 5 degrees eastwards.
A full descriptive geological background of the Lyneham
area can be found here
Lyneham is situated on a small
plateau approximately 500 feet above sea level and to the south
is the Marlborough Downs escarpment. The underlying water
table is considerably close to the surface
and the excess underground water was
a major factor when the Air Ministry decided to acquire
the Lyneham Court estate for future use of the Lyneham
Airbase. There are main ground springs in the hillside
and numerous mapped sites of water wells in the hamlet.
The majority of the springs and water
courseways converge
and flow northwards to Lilybrook stream then topping up
the Tockenham Reservoir. Up to the early 1900's this water
supply was used to propel the paddles in the water
mill at Lyneham.
Nowadays we often see
the underground water, bleed out of the springs
along the Lyneham Banks carriageway roadside and then meandering
from side to side down the road to the former Dauntsey
Wharf Canal. The under surface water is causing serious
layer erosion to the softer foundations and suggestions
have been made to improve the drainage along
the area. To reduce further slip, a series of under
road trenches with better converging irrigation would help
reduce this regular under ground erosion and hence the
subsidence.
The B4069 Lyneham Banks road is notoriously infamous for
the hazardous surface and frequent road subsidence. The
former main western route was in such a serious and dangerous
condition in the early spring of 2004, many villagers campaigned
to the local council and county highways department to
get the road repaired. The road was closed for two weeks
and consequently repaired during May 2004 at a staggering
cost of over £250,000. The road is liable to continual
subsidence, hence the numerous warning signs scattered
along its route.
This roadway was the former A420 Swindon to Chippenham
main trunk route prior to the M4 motorway being opened.
The Wiltshire HGV Freight Network Plan actually pinpoints
the B4069 road as unsuitable for heavy vehicles and consequently
advise HGV to use the approved freight route from the
M4 Junction 17 via the A350 Chippenham and A4 Calne and
A3102 primary roads.
We have regularly witnessed numerous accidents
along the route, hazardous subsidence causing further dangers
to road users, costly repairs at tax payers expense.
History
shows that the underlying water activity will always be
there, we can help the situation from deteriorating, by
drainage improvement, use a form of lateral support
such as a piled structure, use a grib or gabion wall after
ensuring the area was stable by installing sufficient drainage
and most importantly prolonging the costly maintenance
intervals, by reducing or prohibiting the flow of over
weight vehicles.
The
B4069 has been the subject of lengthy discussion on the village
forum and
the census of opinion is for an enforced weight restriction
to be imposed on the B4069 Lyneham Banks as soon as possible.
During the spring
of 2004, we raised concern about the amount of HGV waste
being transported through our village, after being routed
up the B4069 Lyneham Banks road. Opinion polls were conducted
and the results indicated the majority of residents,
equally share a concern over the frequency of out-of-area
industrial waste vehicles in our community.
Viridor Waste Management from Somerset, which we understand part own the landfill
site in Compton Bassett, have been depositing tens of thousand tonnes
of industrial waste in the Wiltshire landfill site. We went into
dialog with the Somerset company, requesting the need to use Compton
Bassett Landfill site and why they have to use the unsuitable roads with over
weight vehicles.
The Viridor
Waste website highlights
company policy "Viridor
has a powerful commitment to customers and the community,
and an excellent track record in protecting and enhancing
the environment" The responses and lack
of initiative, Viridor displayed show the opposite
approach to their company statement, regarding protecting
the environment.
We
did eventually receive a reply from Viridor External
Affairs manager "Viridor has investigated the use
and possibility of alternative routes to Calne Landfill
and of alternative disposal points for the materials being
transported. The findings of the investigation are that
the alternatives do not currently offer viable options
due to the time, inefficiency and availability restraints
of other routes and sites. Viridor therefore intends
to continue to use the B4069 to access Calne
for the foreseeable future and unfortunately the motorway
junctions direct that traffic through Lyneham."
Further questioning Viridor on the requisition
to use this unsuitable route, Viridor advised that they
would now use the approved freight network via Chippenham
and Calne. However, people have still reported seeing
the large vehicles travelling along the B4069 before the
morning rush-hour.
The
Wiltshire County Council "Freight Routes in Wiltshire" guide
clearly shows that the B4069 is not warranted as a local
lorry route for HGV traffic, especially over 7.5 Tonnes.
Further Information
A letter sent to North Wiltshire Mr Gray
from Mr G.C. Batten,
Environmental Services Department,
Wiltshire County Council, dated 1st July 2004, following concern about Lyneham
Banks subsidence and the reply outlines HGVs do typically
cause more damage to the fabric of roads and response to
the weight limit request - Read more. |