M4
Planned Closure
The first overnight closure will take place on one of the
following two dates scheduled for the demolition process:
21.00 Saturday 1st July to 10.00
Sunday 2nd July
21.00 Saturday 8th July to 10.00 Sunday 9th July
We will update you as soon as the second M4 planned closure
details become available.
Eastbound Traffic
Light Vehicle Only: Leave the M4 at J17 and take the
A429 north to Malmesbury, then east on the B4042 to Wootton
Bassett. From Wootton Bassett take the A3102 towards Swindon.
Rejoin the M4 at J16.
Heavy Vehicles: Leave the M4 at J17 and take the A350
south to Chippenham to join the A4. Follow A4 eastwards to
Calne, Then the A3102 north to Swindon (via Lyneham and Wootton
Bassett). Rejoin the M4 at Junction 16.
Westbound Traffic
Both Heavy and Light Vehicles:
Leave the M4 at J16
take the B4005 to Wroughton then A4361 south to join A4 at
Beckhampton. Follow west to Chippenham via Calne. At Chippenham,
follow the A350 north to join M4 at Junction 17.
We have been in consultation with the
InterRoute Communication Manager, Mr Stephen Osborne-Brown,
regarding the increased overnight traffic through Lyneham
and in particular Wootton Bassett. We raised concern that
both projects will conflict owing to the major sewage works
in progress on the Wootton Bassett High Street. We have been
assured that both InterRoute and Wessex Water have been in
regular communication and planned works at the sewage repairs,
should not affect the planned diversions.
The single westward diversion route
has been planned to alleviate congestion routes through Wootton
Bassett on the southbound traffic, should the Wessex Drainage
rework be still in progress. |